The Apartment Turnover Process Step by Step

inspect, trash-out, repairs, paint, floors and clean, punch

The sequence

6 steps

paid renovation in target housing and child-occupied facilities (40 CFR 745.82)

Federal rule that reaches turn paint work

EPA Lead RRP rule

20 sq ft outside; window replacement always covered

EPA minor-repair threshold

6 sq ft per room inside

firm certification: 5 years, $300 ($20 tribal; EPA fee schedule, accessed 2026-10-09)

Certified renovator course

min 8 hours, 2 hands-on

An apartment turnover — the turn, the make-ready process — runs a vacant unit from move-out to rent-ready in a six-step sequence: move-out inspection, trash-out, repairs and replacements, paint, flooring and cleaning, then a final punch and quality check.

This guide walks each step as the make-ready technicians, maintenance techs and supervisors who run unit turnover do it, including the federal lead-paint rule that reaches turn work in housing built before 1978.

Move-out inspection

The turn starts the moment the keys come back.

Before anything is removed, patched or painted, the unit gets its move-out inspection — the walk that sizes every step after it and becomes the property's record of the unit's condition at surrender.

The walk covers every room and every system.

Run water at each fixture, flush every toilet, run each appliance through a cycle, test outlets and switches, open and close doors, windows and closet tracks, and check walls, ceilings, floors, carpet and blinds.

What the inspection separates is chargeable damage from the turnover work the property budgets for — that call drives the scope sheet.

Photograph before anything moves.

Condition photos taken before furniture comes out and before repairs start are what the documentation file stands on later.

California's rules are a worked example, written into Civil Code 1950.5.

On the resident's request, the landlord or agent must make an initial, pre-move-out inspection no earlier than two weeks before the tenancy ends, so the resident can cure what the inspection finds before deductions.

From April 1, 2025, the landlord must photograph the unit within a reasonable time after it is returned — before any repairs or cleaning the landlord will deduct for, and again after those repairs or cleaning are completed.

For tenancies beginning on or after July 1, 2025, the landlord must also photograph the unit immediately before or at the start of the tenancy.

The itemized deposit statement is due no later than 21 calendar days after the tenant vacates, with separate rules when a repair cannot reasonably be completed inside that window.

The inspection's output is the scope sheet: what the in-house turn team repairs, what goes to a vendor, and what the unit needs to hit the property's rent-ready standard.

For the role behind the sequence — staffing, requirements and the closest pay data — our make ready technician career guide covers the job itself.

Documentation rules are state rules

California's photo and 21-day statement rules are California's. Move-out documentation, entry and deposit procedures are set state by state — build your routine on the rules where the property operates, and confirm them with the agency that administers them before you rely on a checklist written for another state.
Looking for make-ready technician jobs? Browse open positions →

Trash-out

Every apartment turn starts with an empty box.

Trash-out clears everything the departing resident left: food from the refrigerator and pantry, bedding and hangers, furniture, and the debris of a packed-up household.

Bag it, stage it to the community's trash point, break down boxes, and build the haul-off list for mattresses and furniture too large for the dumpster.

Items of value left behind are a documentation problem, not a trash problem.

Follow the company's abandoned-property procedure rather than guessing, and photograph anything of apparent value before it leaves the unit.

Watch what you grab: needles in trash bags, broken glass, cleaning chemicals and spoiled food.

Hazardous items go through the property's disposal procedure rather than into the dumpster, and gloves are the default for the whole step.

The step earns its place at the front: an emptied unit shows its real condition.

Patch measurements, paint scuffs and floor damage get judged on bare floors, not around someone's sofa, so the scope sheet from the inspection can be finalized on what the unit actually looks like.

Repairs and replacements

The repair list is the turn's center of gravity: drywall patching, door hardware and adjustments, cabinet and closet-track fixes, faucet and toilet work, outlet and switch replacements, appliance troubleshooting, filters, detector tests, window hardware and rekeying under the community's lock policy.

Repairs finish before paint, so patched walls reach the primer sound and clean; finishes that paint would ruin go back on after.

In housing built before 1978, this step runs under the EPA's Lead Renovation, Repair and Painting (RRP) rule (40 CFR 745.82), which applies to renovations performed for compensation in target housing and child-occupied facilities.

Turn work for a management company is performed for compensation, so the question is whether the building is target housing.

Target housing is housing built before 1978, excluding housing for the elderly or persons with disabilities and 0-bedroom dwellings, unless a child under 6 resides there or is expected to.

The 0-bedroom category includes efficiencies, studio apartments, dormitory housing, military barracks and rentals of individual rooms.

The covered-activity list reaches ordinary turn tasks: repair and maintenance, electrical work, plumbing, painting preparation, carpentry and window replacement in pre-1978 housing.

The exclusion is narrow: minor repair and maintenance that disturbs 6 square feet or less of painted surface per room inside, or 20 square feet or less outside, sits outside the rule.

Two carve-outs from that exclusion matter on turns — window replacement and demolition of painted surfaces are always covered, and, emergency renovations aside, jobs in the same room within 30 days count as one job.

Paint testing is not required by the rule, but unless there is documentation that the paint is not lead-based, the rule's requirements apply.

In a pre-1978 building with no paint records, the file is what settles it.

Who administers the rule varies by state.

Fifteen states run their own RRP programs instead of EPA: Alabama, Delaware, Georgia, Iowa, Kansas, Massachusetts, Mississippi, North Carolina, Oklahoma, Oregon, Rhode Island, Utah, Vermont, Washington and Wisconsin — plus the Bois Forte Band of Chippewa.

Covered work there requires certification under the state or tribal program.

Confirm the rule where the building sits

The thresholds above are EPA rule text; in the fifteen state-program states, the state agency runs its own program, and company policy can be stricter than either. Confirm the current requirements with the EPA, or with your state's lead program, before scheduling paint-disturbing work in a pre-1978 building.

Paint

Paint is the step the lead-paint rule regulates most directly: full repaints, ceiling spot priming, trim enamel and sanding patched walls all disturb painted surfaces.

In a pre-1978 building, the rule shapes who can hold the sprayer and who has to be on site while they do.

The firm comes first.

EPA's guidance for property managers says a company that performs RRP activities in pre-1978 housing must become a Lead-Safe Certified Firm, and a company that does not perform the work must hire only a Lead-Safe Certified firm for jobs that could disturb lead paint.

EPA lists residential rental property owners and managers among the firms that must be certified when they are paid to do paint-disturbing work in pre-1978 housing.

Firm certification lasts five years.

EPA's fee schedule, accessed October 2026, prices renovation firm certification at $300 ($20 for a tribal firm) and a replacement certificate at $15.

Then the crew.

Every renovation needs an assigned certified renovator, and everyone else doing paint-disturbing work for the firm must be a certified renovator or have been trained by one.

The credential itself is a course.

A tech becomes a certified renovator by completing an EPA-accredited renovator course — or a course accredited by an authorized state or tribe — and the course completion certificate is the proof of certification.

The initial course must run at least 8 training hours, with at least 2 hours of hands-on training.

The clock matters for scheduling.

Refresher courses must run at least 4 hours, and a renovator must take one within 5 years of the initial course or retake the initial course.

A refresher with hands-on training certifies for 5 years; one without certifies for 3.

On the unit, the certified renovator must be physically present when warning signs are posted, when containment is set up and when work-area cleaning is done, and must be available on-site or by phone at all times the renovation is under way.

That requirement is one reason pre-1978 paint work gets scheduled around a certified renovator's availability.

Emergency work is treated separately.

Emergency renovations — sudden, unexpected events such as non-routine equipment failures — are partly exempt from the warning-sign, containment, waste-handling, training and certification requirements to the extent needed to respond, but not from the cleaning and cleaning-verification requirements.

Flooring and cleaning

Flooring follows the call the scope sheet made at inspection.

Carpet gets extracted and re-cleaned, re-stretched, patched or replaced; hard surfaces get a deep clean, a re-coat or plank swaps where damage warrants — the property's standard for the unit class decides.

Whatever the call, flooring goes in after paint and before the final clean, so wet paint and new floors never share the same day.

Water damage found during a turn runs on EPA's guidance clock: dry water-damaged areas and items within 24-48 hours, and per the guidance, material dried inside that window will in most cases not grow mold.

Both figures — the 24-48 hour drying window and the 10-square-foot threshold below — are EPA guidance written for homeowners, not regulations, and they do not replace the hazard-communication and protective-equipment duties an employer already has on a job.

Size any mold before anyone starts scrubbing.

Under EPA's guidance, areas “less than about 10 square feet” — less than roughly a 3 ft. by 3 ft. patch — can usually be cleaned without specialists.

With a lot of water damage, or mold growth covering “more than 10 square feet”, EPA points to its remediation guide for schools and commercial buildings.

Anything beyond the team's scope goes to a contractor the property hires.

The clean itself runs top-down: cabinets and drawers wiped inside and out, appliances pulled and cleaned behind, fixtures and fan covers, baths and kitchens sanitized, blinds and tracks, and floors last so grit never tracks back onto a finished surface.

Final punch and QC

The punch is the turn's proof step.

Walk the unit against the scope sheet line by line — every line closed or escalated, nothing marked done that isn't.

Then test the items a move-in walkthrough checks first: every key in every lock, each appliance through a cycle, every faucet and drain, detectors, filters, blinds, doors and closet tracks.

Documentation closes alongside the punch.

Nationally, O*NET lists recording the type and cost of maintenance or repair work among the core tasks of general maintenance and repair workers (SOC 49-9071) — the occupation group used as the closest stand-in for make-ready pay.

On a turn, that task is the file: the scope sheet, the condition photos, the work completed, the materials charged and the punch results.

The release is binary.

The unit goes to the leasing office as rent-ready, or it goes back on the board with a named fix.

Punch photos close the file either way.

Typical timeline

The honest answer on timing is that no published turn-time benchmark turned up in our research.

Operators and vendors quote days-per-turn figures, but those figures are internal targets — repeat one and you are quoting one company's goal, not a number our research could trace to an independent source.

What actually sets the clock is the scope.

A paint-and-clean refresh with the floors already sound moves faster than a unit pulling new carpet and a tub reglaze.

A pre-1978 building adds certified-firm and certified-renovator scheduling to the paint step.

Appliance swaps wait on deliveries, vendor crews wait on calendars, and the move-in date the leasing team has promised bends everything else around it.

The sequence holds regardless of the clock: trash-out before the scope is finalized, repairs before paint, paint before flooring and the final clean, punch last.

Steps swapped are steps redone.

Two compliance clocks are worth a supervisor's calendar.

Firm certification runs five years, and EPA advises applying for recertification at least 90 days before it expires.

Renovators must take a refresher within 5 years of their initial course or retake the initial course — and a refresher without hands-on training certifies for only 3 years.

Either lapse can stall the paint step on the pre-1978 units queued behind it.

Career information, not legal, tax or licensing advice. The lead-paint requirements above are the EPA's Lead RRP rule, administered by the EPA or by a state lead program — confirm the current rules with the agency that runs the program where your property operates.

Frequently Asked Questions

What triggers EPA lead-paint rules in an apartment turnover?

Paid renovation work that disturbs painted surfaces in target housing — housing built before 1978, with exclusions — or in a child-occupied facility.

Covered activities include repair and maintenance, electrical work, plumbing, painting preparation, carpentry and window replacement.

Minor repairs disturbing 6 square feet or less of painted surface per room inside, or 20 square feet or less outside, are outside the rule, but window replacement and demolition of painted surfaces are always covered.

Without documentation that the paint is not lead-based, the rule's requirements apply.

Does every turn tech need to be an EPA certified renovator?

The rule is built firm-first: the company performing covered work in pre-1978 housing must be a Lead-Safe Certified Firm, and each renovation needs an assigned certified renovator.

Other workers doing paint-disturbing work must be certified renovators or trained by one.

The certified renovator course is at least 8 hours with 2 hours of hands-on training, from an EPA-accredited provider or an authorized state or tribal program.

Fifteen states run their own programs instead of EPA — confirm the requirements where you work with the EPA or the state agency.

Who does the work in an apartment turnover?

The site team, split by scope.

Make-ready technicians own the turn sequence end to end; maintenance technicians take the repair-heavy items and the systems work; porters and housekeepers may help with trash-out and the deep clean; and vendors may take flooring replacement, appliance swaps and contract paint crews.

The maintenance or make-ready supervisor sequences the queue against the leasing team's move-in dates.

On a smaller property, one tech may run the whole sequence alone.

What gets documented at move-out?

Condition photos before anything is moved or repaired, the inspection notes, and the scope sheet the rest of the turn works from.

California's rules show how far documentation can go.

Since April 1, 2025, the landlord has had to photograph the unit within a reasonable time after it is returned — before any repairs or cleaning the landlord will deduct for, and again after.

For tenancies beginning on or after July 1, 2025, photographs immediately before or at the start of the tenancy apply as well, and the itemized deposit statement is due no later than 21 calendar days after the tenant vacates.